How to prepare concrete cubes, using cube moulds, for testing?
Clean the cube mould thoroughly and oil it’s inner walls
lightly. Freshly prepared concrete
should be added to the mould and compacted with a steel tamping bar,
with at least 30 to 35 tamps per layer for a 100 mm cube mould. Slightly overfill
the mould and gently trowel the extra concrete to level it with top of mould.
Keep the freshly filled cube mould at a place away from
extreme heat or cold. Also, cover the top with a plastic sheet to prevent
surface evaporation. After 72 hours, extract the concrete cube from cube mould
and place it in the curing tank. After the completion of curing process, concrete
cubes are ready for testing.